Westwood Reconstruction _ Update 2019

Westwood Avenue Reconstruction 2019 

The Town of Wolfville has awarded the contract for the reconstruction of Westwood Avenue to Howard Little Excavating Ltd. The work includes concrete curbs/gutters, sanitary sewer, water, base gravels, asphalt surfaces, concrete sidewalk on the west side of the street and reinstatement of disturbed areas. 

Construction is scheduled to start Wednesday August 28th, 2019 with the removal of existing asphalt and pipe work to begin the week of September 2nd, 2019.

The project is expected to be completed by the end of November 2019.

Hours of work will generally be from 7 am to 7 pm. While construction is ongoing, the work area will be closed to through traffic during work hours, except for emergency vehicles, construction and local resident traffic. 